Seton Dam
Lillooet, BC
Seton Dam
$1.6 Million
Project Overview
Seton Dam balance of plant, was the supply and installation of all electrical work for the upgrade of spill gates at the Seton Dam.
Work included new ridgid steel conduits, under ground condits, new controls and instrucments, new station AC panels, new station DC panels as well as lighting upgrades.
Work started in the spring of 2010 and was completed by the spring of 2011