Hays
Brooks, Alberta
Hays Susbstation
$1.7 Million
Project Overview
Ugrades required to the existing Hays substation located 63 km south of Brooks, Alberta. Work included replacing the existing T1 transformer with one new 138/25kV 25/33/42 MVA LTC Transformer and installing two new 25 kV feed circuit breakers.
Started in May 2014
Completed in October 2014