Beartrap

Bonnyville, Alberta
Beartrap Substation $3 Million

Project Overview

The construction scope for the new 144/4.16 kV Beatrap Substation included all civil, structural and electrical works. Located 24 km east of Bonnyville, AB.

Work included:
• Site Grading
• Supply and install of access roads
• Supply and install of screw pile foundations
• Supply and install of perimeter fencing
• Supply and install of ground grid
• Install equipment steel supports, equipment grillages, lightning spires and stairs
• Install 15/20/25 MVA 144/4.16 kV transformer, 144 KV circuit breaker, disconnect switches, CVT, gang switches and voltage transformers.

Started October 2013

Completed March 2014