Norberg

Central East Alberta
Norberg Substation $675,000

Project Overview

The Norberg project is to meet the increasing demand for the proposed pipeline and AESO reliability criteria. The project included construction of a new substation with an eleven meter control building, one 144kV breaker 701, 144kV -4.16kV 10/13.3/16.1 MVA LTC transformer 701T and NGR.