Mt Hayes LNG

Ladysmith, BC
Mt. Hayes LNG $15.4 Million

Project Overview

Mt Hayes Electrical & Instrumentation of a 1.5 m Gallon LNG Storage Tank with LNG stored at -260F.

Work started in August of 2008 and Opened in June of 2011

Work conducted at this site consisted of:
• Multiple voltage substation primary feed 25kv and MCC distribution systems
• LNG pumps driven by 4160V VFDs
• MOVs and control valves
• Nitrogen generator and Instrument Air System
• Self regulating heating system for process pipe freeze protection with programmable controllers
• firewater system supplying deluge piping distributions
• Clean Agent and Sapphire fire protection systems
• Supply and Install of 350 tons of Structural Steel
• Supply & Install 6 Metal Buildings
• All Electrical Work for a Liquid Natural Gas Plant
• All Instrumentation for a Liquid Natural Gas Plant
• Multiple Motor Control Sections (MCC) ranging in voltage from 4160 and 480 VAC